San Diego County Water Authority
San Diego County Water Authority
About Us
Water Management
SDCWA Infrastructure
SDCWA News Publications
Board of Directors
Education
Opportunities
Contact Us
San Diego County Water Authority

MINUTES OF THE ENGINEERING AND OPERATIONS COMMITTEE

MAY 16, 2005

CALL TO ORDER / ROLL CALL

Chairman Knutson called the Engineering and Operations Committee to order at 1:37 p.m. Committee members present were Vice Chairs Ferguson and Johnson and Directors Brammell, Croucher, Lewanski, Lewinger, and Sundram. Committee members absent were Directors Broomell, Inzunza, Loveland, Rogers, Thompson, and Tu. At that time there was a quorum of the Committee. Staff present was General Manager Stapleton, General Counsel Hentschke, Deputy General Manager Lanspery, Assistant General Manager Cushman, Director of Operations and Maintenance Eaton, Director of Engineering Economides, Director of Right of Way Rose, Assistant Director of Engineering Stift, and Engineering Manager Steele.

SAN VICENTE PIPELINE BID RESULTS

Chairman Knutson informed the committee that the purpose of the meeting was to discuss the bid results, contract award options, and budget implications in order to provide staff direction on the award of the San Vicente Pipeline contract.

Mr. Economides gave a brief overview of the San Vicente Pipeline project, and turned the presentation over to Mr. Steele.

Mr. Steele stated that the construction cost estimate for the project was $161 million, while the bids received were $198 million, $202 million, and $230 million. The design consultant, Jacobs Civil, and staff studied the cost estimate against the bids submitted and found that the cost estimate underestimated the cost and labor of equipment for the project and the amount of time the contractor required to physically tunnel through the various ground conditions.

Committee members Thompson and Tu arrived.

Mr. Mike McRae, from Jacobs, gave a more detailed explanation of the review of the cost estimate comparison, including labor, equipment operating, and current market conditions. The evaluation found explainable discrepancies of $12 million in equipment, $5 million in an omitted blasting restriction, and $20 million in tunneling advance rates. Another item discussed was the increased volume of ongoing tunnel projects throughout the country, where there was over three times the amount of tunnel construction started in 2004 than in past years, which had resulted in competition for labor, as well as contractors taking on less risk and elevated bid prices. After taking those items into consideration, it was determined the cost estimate was comparable to the bids received.

Directors asked questions and made comments about this item.

Director Sundram requested a copy of the ESP cost value study.

Mr. Economides informed the committee that the larger bid price and adding the surge control facility to the San Vicente Pipeline Project would result in an overall $99 million project budget increase, of which $55 million had already been brought to the attention of the Board. Staff provided options to mitigate that budget difference, including deferral of projects, elimination of projects, and a combination of deferral and elimination.

Director Lewinger introduced two motions:

1. Recommend that staff proceed with the San Vicente Pipeline bid award at the June 23, 2005 Board meeting;
2. Convene a Member Agency General Manager’s committee to discuss project deferral and elimination in order to provide a recommendation to the Engineering and Operations committee.

Vice Chair Ferguson seconded, and the motion passed unanimously.

ADJOURNMENT

There being no further business to come before the Engineering and Operations Committee, Chairman Knutson adjourned the meeting at 3:07 p.m.


______________________________
Bill Knutson
Chair, Engineering and Operations